Application of SLP and TPM to Increase the Complete Order Rate at an MSE
DOI:
https://doi.org/10.4108/dtip.15609Keywords:
Discrete Event Simulation, Complete orders rate, Metalworking industry, MSE, OEE, SLP, TPMAbstract
The research aimed to increase the Complete Order Rate (COR) in a micro and small enterprise (MSE) dedicated to manufacturing cardboard binders. The company presented a low COR of 76.21%, resulting in an estimated economic impact equivalent to 5.1% of revenue from these products. The three main root causes identified were delays during the production process, obstructions caused by materials and pallets, and the absence of a formal maintenance system. To address these issues, Systematic Layout Planning (SLP) was proposed for the plant, while Total Productive Maintenance (TPM) was implemented through a pilot test exclusively on the riveting machine. The Arena simulation results showed a 20.98% increase in the Complete Order Rate, together with similar improvements in Overall Equipment Effectiveness (OEE) and in partial machinery productivity. The TPM pilot test provided the maintenance-time data used to parameterize the proposed simulation scenario.
Downloads
References
[1] Ministry of Production. PRODUCE: Manufacturing GDP grew by 5.5% in January 2025, marking 10 consecutive months of growth [Internet]. Lima: Government of Peru; 2025 Mar 12 [cited 2026 Nov 6]. Available from: https://www.gob.pe/institucion/produce/noticias/1125014-produce-pbi-manufactura-crecio-5-5-en-enero-de-2025-y-acumulo-10-meses-de-avance-continuo
[2] International Labour Organization. Impulsando la productividad en América Latina: informe regional 2023 [Internet]. Geneva: International Labour Organization; 2023 [cited 2026 Oct 16]. Available from: https://www.ilo.org/sites/default/files/wcmsp5/groups/public/@ed_dialogue/@act_emp/documents/publication/wcms_906015.pdf
[3] Becerra AM, Villanueva AR. Propuesta de reducción de tiempo de entrega de pedidos en una Mype del sector gráfico en Lima mediante la utilización de herramientas Lean Manufacturing como VSM, SMED y Kanban [Internet]. Lima: Repositorio Académico UPC; 2020 [cited 2026 Oct 16]. Available from: http://hdl.handle.net/10757/652562
[4] Castro AM, Pérez JR. Application of total productive maintenance in a manufacturing process of cardboard boxes under Lean Six Sigma DMAIC methodology. South African Journal of Industrial Engineering. 2024; 35(4):37–51. doi:10.7166/35-4-3068.
[5] Prasetyani R, Siti A, Timang GA. Design of facility location for new model of medical pharmaceutical refrigerator production area on PT XYZ. IOP Conference Series: Materials Science and Engineering. 2020; 847:012009. doi:10.1088/1757-899X/847/1/012009.
[6] Díaz B, Jarufe Zedán B, Noriega Araníbar de Lavalle MT. Disposición de planta. Lima: Universidad de Lima; 2013.
[7] Chen TJ, Lee YC, Chiang CH. Optimizing production layout and capacity via FlexSim: A case study of Y factory. IOP Conference Series: Materials Science and Engineering. 2020; 847:012029. doi:10.1088/1757-899X/847/1/012029.
[8] Dextre-Del-Castillo D, Urruchi-Ortega S, Peñafiel-Carrera J, Raymundo-Ibañez C, Dominguez F. Lean manufacturing production method using the change management approach to reduce backorders at MSEs in the footwear industry in Peru. IOP Conference Series: Materials Science and Engineering. 2020; 796:012021. doi:10.1088/1757-899X/796/1/012021.
[9] Tarigan U, Ishak A, Tarigan UPP, Rizkya I, Mangoloi B, William. Redesigning production floor layout with process layout and product layout approach in an electronic appliance manufacturing company. IOP Conference Series: Materials Science and Engineering. 2021; 1122:012058. doi:10.1088/1757-899X/1122/1/012058.
[10] Leon Taipe AM, Baquerizo Santillan CM. Aplicación del Planeamiento Sistemático de Planta (SLP) y balance de línea para reducir los pedidos no entregados a tiempo e incompletos en la empresa CORPABER SAC [trabajo de suficiencia profesional]. Lima: Universidad Peruana de Ciencias Aplicadas; 2023. Disponible en: http://hdl.handle.net/10757/671616
[11] Gao, G., Feng, Y., Zhang, Z., Wang, S., & Yang, Z. (2023). Integrating SLP with simulation to design and evaluate facility layout for industrial head lettuce production. Annals of Operations Research, 321(1–2), 209–240. https://doi.org/10.1007/s10479-022-04893-z
[12] Vij R, Singh S. Improving the productivity and efficiency of Indian cycle industry through TPM. IUP Journal of Operations Management. 2024; 23(3):48–63.
[13] Hossen MT, Rafiquzzaman M, Manik YA. Productivity improvement through lean tools in cement industry: A case study. Heliyon. 2025; 11(3):e42057. doi:10.1016/j.heliyon.2025.e42057.
[14] Farah M, Montaño S, Quiroz JC. Enhancing productivity in agricultural packing operations through TPM and lean manufacturing: A case study of asparagus processing in Peru. SSRG International Journal of Mechanical Engineering. 2024; 11(11):1–14. doi:10.14445/23488360/IJME-V11I11P101.
[15] Guillen J, Depaz AM. Mantenimiento productivo total en la eficiencia productiva de las empresas industriales: una breve revisión de literatura. Signos. 2024; 16(1):1–18. doi:10.15332/24631140.8807.
[16] Florez RM, Huamán CE, Quiroz J. Improving productivity in an MSE in the metalworking sector through lean manufacturing and TPM tools: A case study in Peru. South African Journal of Industrial Engineering. 2024; 35(2):91–109. doi:10.7166/35-2-3013.
[17] Sumastro F, Safitri IN, Imansuri F, Indra RP, Wulansari I, Solih ES, Dzulfikar A. Enhancing overall equipment effectiveness in Indonesian automotive MSEs: A TPM approach. Journal Européen des Systèmes Automatisés. 2024; 57(2):383–396. doi:10.18280/jesa.570208.
[18] Jaqin, C., Rozak, A., & H, H. P. (2020). Case Study in Increasing Overall Equipment Effectiveness on Progressive Press Machine Using Plan-do-check-act Cycle. International Journal Of Engineering. Transactions B: Applications, 33(11). https://doi.org/10.5829/ije.2020.33.11b.16
[19] Contreras-Rios V, Cortavarría-Cruz M, León-Chavarri C, Alvarez JC, Lepore R. Process optimization through the implementation of SLP, Kanban, Poka-Yoke and TPM to improve efficiency in a metalworking SME. Int J Eng Trends Technol. 2025;73(6):269–280. doi:10.14445/22315381/IJETT-V73I6P122
[20] Calderón G, Zavala L, Velásquez-Costa J, Losada-Gutiérrez C. Model to improve efficiency in the production of metal protectors for motorcycles by applying SLP and TPM 4.0 with Industry 4.0. Adv Transdiscip Eng. 2026; DOI:10.3233/ATDE260708.
[21] Fuentes EA, Parra IC, Cañón ON. Desarrollo de herramientas lean manufacturing para la línea de producción en Printer Colombiana SAS. Revista Ingeniería, Matemáticas y Ciencias de la Información. 2022; 9(17):45–62. doi:10.21017/rimci.2022.v9.n17.a110.
[22] Fikry I, Zamzam N. An integrated decision-support workflow for facility layout planning. Appl Syst Innov. 2026;9(7):156. doi:10.3390/asi9070156.
[23] Ministerio de Vivienda, Construcción y Saneamiento. Reglamento Nacional de Edificaciones: Norma A.120, Accesibilidad universal en edificaciones [Internet]. Lima: Ministerio de Vivienda, Construcción y Saneamiento; 2006 [cited 2026 Oct 11]. Available from: https://cdn.www.gob.pe/uploads/document/file/4175227/46%20A.120%20ACCESIBILIDAD%20UNIVERSAL%20EN%20EDIFICACIONES
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Ariana Andrea Vargas Pinto, Ariana Zevallos Calderon, María Teresa Noriega-Aranibar

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
This is an open access article distributed under the terms of the CC BY-NC-SA 4.0, which permits copying, redistributing, remixing, transformation, and building upon the material in any medium so long as the original work is properly cited.