A State-Updated Constraint Propagation Method for BIM–Digital Twin-Driven Local Rescheduling in Prefabricated Component Manufacturing

Authors

  • Jiankang Wu Hainan Vocational University of Science and Technology image/svg+xml
  • Xiaozhu Li Hainan Vocational University of Science and Technology image/svg+xml

DOI:

https://doi.org/10.4108/eetsis.13902

Keywords:

artificial intelligence in manufacturing, digital twin, BIM/IFC, state-updated constraint propagation, local rescheduling, schedule stability

Abstract

INTRODUCTION: Prefabricated component manufacturing requires adaptive rescheduling when equipment failures, delays, resource shortages, or order changes invalidate original production plans. Existing approaches often rely on predefined disturbances or global re-optimization and do not sufficiently connect BIM/IFC-derived constraints with digital-twin state feedback.

OBJECTIVES: This study aims to develop a stable local rescheduling framework that continuously maps BIM/IFC component relationships and digital-twin state deviations into dynamic constraints, affected task sets, rescheduling triggers, and local repair boundaries.

METHODS: A BIM-DT state-updated constraint propagation mechanism was designed to transform floor sequences, assembly dependencies, operation precedence, mold compatibility, and resource capacity into initial constraints, and then update them using equipment-state deviations. A constraint-driven local rescheduling module was further developed using task locking, local repair windows, state-triggered activation, and adaptive schedule-stability control. Reconstructed experiments were conducted using OR-Library scheduling instances and NASA C-MAPSS equipment-state data.

RESULTS: Across five repeated experiments, the proposed method achieved lower total tardiness, rescheduling cost, schedule deviation, and adjusted-task ratios than most baseline methods under reconstructed disturbance scenarios. Compared with the best-performing dynamic baseline in this comparison, ND3QNP, total tardiness decreased from 101.8 to 96.4 on OR-Library and from 131.7 to 126.5 on C-MAPSS. Ablation and representation analyses provided supporting evidence for the roles of constraint propagation, state triggering, local repair, task locking, and adaptive stability control.

CONCLUSION: The framework provides a reproducible constraint-driven local repair method for disturbance-oriented rescheduling in prefabricated component manufacturing, while future validation with real factory BIM-DT data remains necessary.

References

[1] Liu, H., & Zainul Abidin, N. (2024). A review on research of prefabricated building costs: exploring collaborations, Intellectual Basis, and research trends. Sustainability, 16(22), 9823.

[2] Wang, L., Teng, D., Jin, R., Guo, X., Meng, X., Liu, G., ... & Su, Z. (2025). The development of prefabricated buildings and intelligent construction based on digital twins. Journal of Intelligent Construction, 3(1), 1-25.

[3] Yang, Y., Yu, Y., Yu, C., & Zhong, R. Y. (2024). Data-driven logistics collaboration for prefabricated supply chain with multiple factories. Automation in Construction, 168, 105802.

[4] Wang, Z., & Xu, H. (2024). Scheduling redundancy optimization for precast production to enhance disruption management in prefabricated construction. Computers & Industrial Engineering, 192, 110251.

[5] Ho, C., Zabinsky, Z. B., & Kim, Y. W. (2026). Scheduling the production of prefabrication construction supply chains considering variable delivery times. Journal of Civil Engineering and Management, 32(3), 415-432.

[6] Liang, J., Cao, Z., Zu, Q., Huang, H., & Guo, S. (2024). Production sequencing and layout optimization of precast concrete components under mold resource constraints. Buildings, 14(10), 3173.

[7] Zhang, C., Jiang, J., Xia, C., Fu, Y., Liu, J., & Duan, P. (2024). Dual-objective optimization of prefabricated component logistics based on JIT strategy. Scientific Reports, 14(1), 31267.

[8] Amarkhil, Q., & Elwakil, E. (2026). A novel framework for structuring and automating schedule-ready data from BIM for advanced construction scheduling. J. Inf. Technol. Constr., 31, 651-673.

[9] Gao, M. Y., Han, J., Yang, Y., Tiong, R. L., Zhao, C., & Han, C. (2024). BIM-based and IoT-driven smart tracking for precast construction dynamic scheduling. Journal of Construction Engineering and Management, 150(9), 04024117.

[10] Chacón, R., Posada, H., Ramonell, C., Jungmann, M., Hartmann, T., Khan, R., & Tomar, R. (2024). Digital twinning of building construction processes. Case study: A reinforced concrete cast-in structure. Journal of Building Engineering, 84, 108522.

[11] Li, S., Peng, C., Chen, G., Liang, Y., & Xu, Z. (2025). Swarm-intelligence collaboration based regular scheduling and dynamic rescheduling of precast component production: in prefabricated building project management. Smart Construction, 2(1), 1-30.

[12] Zheng, R., Li, Z., Li, L., Dou, Y., Yuan, M., & Yin, X. (2024). Proposing a lean-optimized scheduling model of mixed-flow prefabricated component production in off-site construction. Journal of Construction Engineering and Management, 150(8), 04024088.

[13] Zhao, Y., Du, S., Tu, M., Ma, H., Shang, J., & Xiang, X. (2025). Multi-Objective Scheduling Optimization of Prefabricated Components Production Using Improved Non-Dominated Sorting Generic Algorithm II. Buildings, 15(5), 742.

[14] Dan, Y., Sun, C., & Luo, Q. (2025). Integrated scheduling optimization for multi-line production and transportation of prefabricated components considering shared resources. Buildings, 15(2), 187.

[15] Yu, M., Ruan, W., Zhou, Y., & Zhao, Y. (2025). Flow shop scheduling for prefabricated components production considering parallel machines and buffer constraints. Journal of Construction Engineering and Management, 151(4), 04025010.

[16] Qian, Y., Mao, N., Yu, J., & Shi, Q. (2025). Optimization of Precast Concrete Production with a Differential Evolutionary Algorithm. Buildings, 15(23), 4226.

[17] Zhang, D., Zhang, H., Chen, D., Zhang, Y., & Wu, X. (2024). A review of production scheduling for prefabricated building components. Voice of the Publisher, 10(1), 11.

[18] Kosse, S., Betker, V., Hagedorn, P., König, M., & Schmidt, T. (2024). A semantic digital twin for the dynamic scheduling of industry 4.0-based production of precast concrete elements. Advanced Engineering Informatics, 62, 102677.

[19] Yu, M., Wang, L., Ruan, W., & Zheng, W. (2025). Robust Optimization for Precast Component Production Scheduling Considering Component Transfer. Journal of Construction Engineering and Management, 151(10), 04025156.

[20] Li, Y., Zhao, Q., Yang, M., Ma, Z., & Hei, X. (2025). Advancements and Applications of Industry Foundation Classes Standards in Engineering: A Comprehensive Review. Buildings, 15(16), 2927.

[21] Doan, D. T., Atencio, E., Muñoz La Rivera, F., & Alnajjar, O. (2025). A Systematic Literature Review of Building Information Modelling (BIM) and Offsite Construction (OSC) Integration: Emerging Technologies and Future Trends. Applied Sciences, 15(18), 9981.

[22] Aghajamali, K., Rahimi, A., Metvaei, S., Lei, Z., Chen, Q., Suliman, A., & Pirzad, A. (2026). Production planning with an enriched BIM-Based heuristic construction order model to improve the efficiency of complex prefabricated projects. Journal of Construction Engineering and Management, 152(6), 04026057.

[23] Belsky, M., Sacks, R., & Brilakis, I. (2016). Semantic enrichment for building information modeling. Computer‐Aided Civil and Infrastructure Engineering, 31(4), 261-274.

[24] Liu, Z., Li, X., Gao, Z., Zhang, Y., Teng, Y., & Wu, C. (2025). A hybrid and intuitive work packaging approach with multiple task relations, general work package precedence, and BIM in modular construction. Journal of Construction Engineering and Management, 151(4), 04025019.

[25] Chong, H. Y., Yang, X., Goh, C. S., & Luo, Y. (2025). BIM and AI Integration for Dynamic Schedule Management: A Practical Framework and Case Study. Buildings, 15(14), 2451.

[26] Osadcha, I., Jurelionis, A., & Fokaides, P. (2024). Patterns and trends in the use of RFID within the construction industry and Digital Twin architecture: A Latent Semantic Analysis. International Journal of Sustainable Energy, 43(1), 2421281.

[27] Gao, M. Y., Han, C., Yang, Y., & Tiong, R. L. K. (2024). Integration of BIM and RFID-sensing technology for automated progress monitoring in modular construction. In Proceedings of the 41st International Symposium on Automation and Robotics in Construction (ISARC 2024) (pp. 1033–1039). International Association for Automation and Robotics in Construction.

[28] Sheenan, S., Elghaish, F., Brooks, T., & Rahimian, F. (2026). IoT-Enabled Digital Twin for Autonomous Modular Construction Progress Monitoring. ABC2: Journal of Architecture, Building, Construction, and Cities, 2026(02), 23-37.

[29] Elghaish, F., Mohandes, S. R., Rahimian, F., Abrishami, S., & Hosseini, M. R. (2026). Predictive digital monitoring of construction resources: An integrated digital twin solution. Engineering, Construction and Architectural Management, 33(8), 6094-6118.

[30] Park, J., Kim, S., & Lim, J. (2025). Integrated Digital Twin and BIM Approach to Minimize Environmental Loads for In-Situ Production and Yard-Stock Management of Precast Concrete Components. Applied Sciences, 15(17), 9846.

[31] Kim, T., & Kim, Y. W. (2024). Proactive Production Scheduling Approach for Off-Site Construction with Due Date Uncertainty. Applied Sciences, 14(23), 11017.

[32] Yao, Y., Tam, V. W., Wang, J., Le, K. N., & Butera, A. (2025). Deep reinforcement learning-based schedule optimization for parallel precast production. Engineering, Construction and Architectural Management, 32(13), 285-318.

[33] Zheng, T., Li, D., & Li, J. (2025). A Rescheduling Strategy for Multipurpose Batch Processes with Processing Time Variation and Demand Uncertainty. Processes, 13(2), 312.

[34] Panwalkar, S. S., & Iskander, W. (1977). A survey of scheduling rules. Operations research, 25(1), 45-61.

[35] Perron, L., Didier, F., & Gay, S. (2023). The CP-SAT-LP solver (invited talk). In 29th International Conference on Principles and Practice of Constraint Programming (CP 2023) (Vol. 280, pp. 3:1–3:2). Schloss Dagstuhl–Leibniz-Zentrum für Informatik.

[36] Li, X., & Gao, L. (2016). An effective hybrid genetic algorithm and tabu search for flexible job shop scheduling problem. International Journal of Production Economics, 174, 93-110.

[37] Luo, S. (2020). Dynamic scheduling for flexible job shop with new job insertions by deep reinforcement learning. Applied Soft Computing, 91, 106208.

[38] Song, W., Chen, X., Li, Q., & Cao, Z. (2022). Flexible job-shop scheduling via graph neural network and deep reinforcement learning. IEEE Transactions on Industrial Informatics, 19(2), 1600-1610.

[39] Ren, F., & Liu, H. (2024). Dynamic scheduling for flexible job shop based on MachineRank algorithm and reinforcement learning. Scientific reports, 14(1), 29741.

[40] Liu, Y., Zhang, F., Sun, Y., & Zhang, M. (2025). Evolutionary trainer-based deep Q-network for dynamic flexible job-shop scheduling. IEEE Transactions on Evolutionary Computation, 29(3), 749–763.

[41] Yi, W., Deng, Q., Wang, B., Chen, Y., & Pei, Z. (2025). Dynamic flexible job shop scheduling problem considering multiple types of dynamic events. International Journal of Production Research, 63(24), 10291-10308.

[42] Zheng, L., Chen, X., Zhuang, C., Liu, J., Zhang, Y., & Lai, L. (2025). Dynamic scheduling for flexible job-shop with reconfigurable manufacturing cells considering dynamic job arrivals based on deep reinforcement learning. International Journal of Production Research, 63(20), 7427-7459.

Downloads

Published

12-10-2026

Issue

Section

Resiliency and Adaptability for Future Manufacturing: AI Driven Recovery and Response Mechanisms

How to Cite

1.
Wu J, Li X. A State-Updated Constraint Propagation Method for BIM–Digital Twin-Driven Local Rescheduling in Prefabricated Component Manufacturing. EAI Endorsed Scal Inf Syst [Internet]. 2026 Oct. 12 [cited 2026 Oct. 14];13(6). Available from: https://publications.eai.eu/index.php/sis/article/view/13902